Proposed 2017 Capital Projects

e-mail icon

Project

Spinnaker Dr Area Drainage Improvements (15-14)

Community Council

Sponsor Agency

Project Management and Engineering

Estimated Cost

$5,000,000

Funds on hand

$400 000

Additional funds required

$4,600,000

Project scope

Replace the storm drain system and replace pavement and curbs as warranted.

Project need

The existing storm drain system is in a state of imminent failure or collapse. This need was identified by Street Maintenance.

Project status

Design was funded with 2015 road bonds. Scope of work assessment, field investigations and preliminary design currently underway. Attended Huffman/O'Malley Community Council Meeting and presented project.

Project Comments

Log in or register to post comments