Proposed 2017 Capital Projects

e-mail icon

Project

92nd Ave Extension - King St to Old Seward Hwy

Community Council

Sponsor Agency

Project Management and Engineering

Estimated Cost

$18,000,000

Funds on hand

$0

Additional funds required

$18,000,000

Project scope

Improvements would include a new road base, pavement, curbs, drainage, lighting, pedestrian facilities, signals, and an Alaska Railroad underpass.

Project need

This project would complete an east/west transportation corridor serving the Dimond Center area. With the State DOT's construction of an underpass at the Seward Highway, the need and usefulness of a continued connection to the west increases.

Project status

This project has not started. State grant funding is proposed.

Project Comments

Log in or register to post comments