Proposed 2017 Capital Projects

e-mail icon

Project

80th Ave Extension/Upgrade - Spruce St to Elmore Rd

Community Council

Sponsor Agency

Project Management and Engineering

Estimated Cost

$21,000,000

Funds on hand

$0

Additional funds required

$21,000,000

Project scope

This project would extend and upgrade this major local road to urban collector standards. Improvements are expected to include pavement, curbs, storm drains, pedestrian facilities, street lights, water line installation, and landscaping.

Project need

This project has been suggested as an east/west road connector. However, no studies regarding need have been completed or are planned.

Project status

No work is currently scheduled in the 6-year Capital Improvement Program. No funding is planned unless the road is reclassified as a collector street.

Project Comments

Log in or register to post comments